NAIAX WESTBOUND OFF-RAMP, Terminal 3
This new ramp will provide a direct and efficient route for vehicles heading to Terminal 3, alleviating traffic congestion on surrounding roads, as BAUER Philippines constructed seven bored piles (2500mm and 3000mm diameter, up to 23m deep). Two piles had to be positioned between skyway girders, demanding careful planning. Additionally, space constraints necessitated disassembling and reassembling equipment for certain pile locations.
BAUER Foundations Philippines, Inc.
Along Andrews Ave., Pasay City, Philippines
NAIAX Westbound Off-Ramp, Terminal 3
August 2024 to October 2024
Foundation work, Bored Piles
NAIAX Westbound Off-Ramp to Terminal 3