Improvement of Pasig-Marikina River Channel

Drilling and backfilling works

BAUER Philippines implemented offshore replacement drilling along the Marikina River for a flood control and drainage project. The work involved pre-drilling 1,505 positions of Ø1500mm totaling 22,644 lm, followed by sand and/or soil backfilling to improve soil conditions for steel sheet piles. The drilling was done using BG40 with double wall casings through rock layers, supporting the construction of a reinforced concrete flood wall.

Facts about the project
Company :

BAUER Foundations Philippines, Inc.

Location :

Obrero St., Brgy. Bagumbayan, Quezon City, Metro Manila, Philippines

Project Name :

Flood Protection, Marikina River

Period :

May 2023 to February 2024

Services :

Pre-drilling and Sand Backfilling

Pasig-Marikina River Channel Improvement

Are you starting a project?

Get in touch with us.

BAUER Foundations Philippines, Inc.

12th Floor Units A-K, Cyber One Building
11 Eastwood Avenue
Eastwood City Cyberpark
Bagumbayan Quezon City 1110 Metro Manila